Midgard was retained by NU-E Corp to act as the Study Consultant for several proposed solar projects located in Alberta, including a 17 MW, 40 MW, 9 MW (Behind the Fence), 140 MW, and 300 MW connection projects. Midgard's role has involved conducting connection studies in collaboration with AESO, including power flow and short-circuit analyses in PSS/E. Power flow analysis was performed for high solar generation during summer peak and light loading scenarios, both pre- and post-project, with sensitivity analysis for summer peak loading. Short-circuit analysis covered pre- and post-project scenarios to assess short-circuit levels in the project's vicinity.Midgard is actively supporting these projects through AESO's new Connection Process "Cluster Assessments," preparing System Access Service Requests, Project Data Update Packages, and reviewing study scopes and project plans. The projects are currently in Stage 2 of the AESO connection process, with Midgard continuing to provide ongoing support as they progress through further stages. Additionally, for the 9 MW BTF solar project, Midgard conducted an anti-islanding screening study to meet AESO's Distributed Energy Resources ("DER") requirements.
Midgard was retained by YEC to conduct a variety of System Impact Studies ("SIS") for a variety of Independent Power Producer ("IPP") and photovoltaic ("PV") additions to the Yukon electrical grid. SIS are powerflow and short circuit analysis studies of the Yukon electrical grid to evaluate the addition of new energy sources, such as solar panels or generation units. SIS included:
1. Diesel Rental Support – Midgard evaluated the addition of seven (7) 1.8 MW diesel rental units.
2. Haines Junction IPP – Midgard evaluated the addition of a 1 MW AC Solar IPP onto the 25 kV transmission line to Haines Junction.
3. Partridge PV PP – Midgard evaluated the addition of a 2 MW solar PV generator, northeast of the Klondike Highway at the Partridge Farm.
4. Northern Bluebird PV IPP – Midgard evaluated the addition of a 2 MW solar PV generator at kilometer #63 of the Silver Trail Highway.
5. Carcross PV IPP – Midgard evaluated the addition of a 2 MW (with potential expansion to 4 MW) solar PV generator near the community of Carcross, into the ATCO-owned 34.5 kV electrical system.
6. ArcticPharm PV IPP – Midgard evaluated the addition of a 2 MW (with potential expansion to 4 MW) solar PV generator, approximately 20km away from the Laberge Substation (#21) on the Yukon Interconnected Grid.
Midgard Consulting Inc. has been commissioned by the Ontario Finance Authority (agency of the province of Ontario, Canada) to complete due diligence reviews of various renewable energy and transmission projects. The purpose of the program is to assess the suitability of equity loan guarantees needed to facilitate equity participation by local Aboriginal communities in renewable generation projects. The financial, business, and technical review and due diligence effort consists of reviewing contractual, financial and development documentation, Aboriginal participation agreements (e.g., partnerships/corporate structuring), energy forecasts and modelling, operating and maintenance forecasts, robustness and reliability of design, construction works, and other commercial conditions. The list of projects evaluated under this program are:
Midgard was retained by the IESO to perform a series of investigative tasks on procurement issues to assist the system operator with ongoing issues related to their medium-term procurement program. Work conducted to date has provided in depth research and analysis on a variety of procurement issues as detailed here:
Midgard was retained by DBS Energy to assist with the following rehabilitation work:
Midgard was engaged by Newfoundland & Labrador Hydro ("NLH") to develop an Integrated Resource Plan ("IRP") for five remote communities in Southern Labrador, characterized by extreme climate conditions. The objective of the study was to assess various renewable and energy storage technologies, along with different interconnection and transmission options. Within this scope, Midgard conducted a comprehensive evaluation to provide NLH with recommendations that address the energy requirements of the remote communities. The recommendations aim to be both economically viable and consider renewable initiatives and funding opportunities in the evaluation process. The IRP is designed to align with the unique challenges posed by extreme climate conditions in Southern Labrador.The scope of work included:
Midgard was retained by the Electric Utility of City of Lethbridge to serve as the Study Consultant for its 8.75 MW Solar project located in Alberta. In this role, Midgard collaborated with AESO on behalf of NU-E Corp to conduct various connection studies for the project. These studies encompassed power flow analysis, voltage stability analysis, and short-circuit analysis.Power flow analysis was conducted for both the Summer Peak (SP) and Winter Peak (WP) scenarios, both pre- and post-Project, to assess the impact of the project's connection on the Alberta Interconnected Electric System (AIES). Voltage stability analysis was specifically performed for the WP post-Project scenario to identify any potential violations of voltage stability criteria. Additionally, short-circuit analysis was carried out for the WP pre-Project scenario, as well as the WP and WP post-Project scenarios, to determine short-circuit levels in the project's vicinity.